How to Evaluate a Curtain Wall Supplier from China: A Buyer's Checklist

By the YIFU technical team · 8 min read

Most problems with overseas façade procurement — late delivery, leaky units, missing documentation — are visible in the first two weeks of the relationship, long before any panel is made. This checklist is what we would verify if we were buying from a factory like ours.

1. Is it a factory, or a trader with a nice website?

Ask for a live video walk of the production floor — not a promotional video, but a call where you control the camera and ask to see a specific line. A real manufacturer will do this within a day. Check business scope on their licence: "manufacturing" vs "trading". Ask which machines they own and how many assembly lines run.

2. Can they show project-specific test reports?

Generic certificates prove little. Ask for a project mock-up report from a recent export project — air, water and structural results to ASTM E283/E331/E330 or EN 12152/12154/12179. If they only have GB-standard reports, ask whether they can test to your standard and who issues the report.

3. What exactly is included in the price?

Quotes differ wildly on six items: gaskets and sealants, hardware, embeds and brackets, packing (A-frames vs loose), spare units, and Incoterms. A quote that looks 15% cheaper often excludes two of these. Insist on a line-itemed quotation.

4. Who does the shop drawings — and how fast?

Design-assist turnaround is the best single predictor of how the whole project will run. Ask for shop drawings and calculations on a sample condition within 5 working days. Slow, vague engineering responses now mean slow RFIs on site later.

5. How are units packed for sea freight?

Ask for real packing photos from a recent shipment: steel A-frames, vertical storage, EPDM separators, corner protection, VCI film. Units shipped loose on pallets arrive as a claim letter.

6. What does communication look like after the deposit?

Ask for a sample weekly progress report from a current project — photos, output numbers, QC records, next-week plan. And agree a response SLA (24 hours) in writing before signing.

7. What happens when something goes wrong?

Ask for their claim history and procedure: how replacement units for transit damage are handled, typical lead time, and who pays freight. A supplier with no documented process will invent one under pressure — usually badly.

Use the checklist as your tender annex

Put all seven items into your RFQ as required submissions. Manufacturers who respond completely and quickly are the ones who will perform on site. You can also hand the whole evaluation to us — request our standard documentation pack with any enquiry.